Filing changes

The same project compared across two filings: 58 changed fields on 31 projects. A changed in-service date is a change in the filing, not evidence of a current delay.

  1. Dominion Energy SCOkatie 230-115kV Substation, Jasper – Yemassee 230kV #1 Fold-inDESC:0139 M,Nverified exampleno overlap
    • Estimated cost
      $11,116,933changed to$11,630,257+4.6% as filed
      DESC filing 2024-2028, p. 3 → DESC filing 2025-2029, p. 2
    • In-service date
      2024-12-31changed to2026-05-31filed date moved 516 days later between filingshistorical
      DESC filing 2024-2028, p. 3 → DESC filing 2025-2029, p. 2
  2. Dominion Energy SCJack Primus 115 kV Tap: ConstructDESC:0147 B, Jno overlap
    • Estimated cost
      $18,000,000changed to$17,955,000-0.3% as filed
      DESC filing 2024-2028, p. 38 → DESC filing 2025-2029, p. 32
    • In-service date
      2027-12-31changed to2028-12-31filed date moved 366 days later between filings
      DESC filing 2024-2028, p. 38 → DESC filing 2025-2029, p. 32
  3. Dominion Energy SCCainhoy 115 kV Tap: ConstructDESC:0147 C, Kno overlap
    • Estimated cost
      $21,850,000changed to$21,800,000-0.2% as filed
      DESC filing 2024-2028, p. 37 → DESC filing 2025-2029, p. 31
    • In-service date
      2027-12-31changed to2028-12-31filed date moved 366 days later between filings
      DESC filing 2024-2028, p. 37 → DESC filing 2025-2029, p. 31
  4. Dominion Energy SCCanadys-Ritter 115KV-Rebld SPDC 230/115KV 1272 (Approx 18 Miles)DESC:06076Ano overlap
    • Estimated cost
      $40,000,000changed to$38,041,268-4.9% as filed
      DESC filing 2024-2028, p. 20 → DESC filing 2025-2029, p. 15
    • In-service date
      2026-06-01changed to2028-06-01filed date moved 731 days later between filings
      DESC filing 2024-2028, p. 20 → DESC filing 2025-2029, p. 15
  5. Dominion Energy SCSherwood Tap: Construct TapDESC:06367 A - C, Hno overlap
    • Estimated cost
      $34,877,427changed to$54,446,256+56.1% as filed
      DESC filing 2024-2028, p. 22 → DESC filing 2025-2029, p. 17
    • In-service date
      2025-12-31changed to2026-05-31filed date moved 151 days later between filingshistorical
      DESC filing 2024-2028, p. 22 → DESC filing 2025-2029, p. 17
    • Project name
      Riverport Tap: Construct Tapchanged toSherwood Tap: Construct Tap
      DESC filing 2024-2028, p. 22 → DESC filing 2025-2029, p. 17
  6. Dominion Energy SCJasper – Okatie 230 kV #2: ConstructDESC:06367 D - Gin 1 overlap →
    • Estimated cost
      $23,787,423changed to$28,578,734+20.1% as filed
      DESC filing 2024-2028, p. 23 → DESC filing 2025-2029, p. 18
    • In-service date
      2025-12-31changed to2026-05-31filed date moved 151 days later between filingshistorical
      DESC filing 2024-2028, p. 23 → DESC filing 2025-2029, p. 18
  7. Dominion Energy SCWagener 115kV Tap: Construct TapDESC:06371 Dno overlap
    • In-service date
      2025-12-31changed to2027-12-31filed date moved 730 days later between filings
      DESC filing 2024-2028, p. 24 → DESC filing 2025-2029, p. 19
  8. Dominion Energy SCChurch Creek - Ritter 230kV - Replace 38 Large Angles and Dead EndsDESC:06372 Ano overlap
    • Estimated cost
      $10,850,000changed to$11,401,163+5.1% as filed
      DESC filing 2024-2028, p. 25 → DESC filing 2025-2029, p. 20
    • In-service date
      2024-06-01changed to2025-12-31filed date moved 578 days later between filingshistorical
      DESC filing 2024-2028, p. 25 → DESC filing 2025-2029, p. 20
  9. Dominion Energy SCVCS2-Ward 230kV: Rebuild LineDESC:06810 Fno overlap
    • Estimated cost
      $30,000,000changed to$38,275,000+27.6% as filed
      DESC filing 2024-2028, p. 26 → DESC filing 2025-2029, p. 21
  10. Dominion Energy SCGoose Creek Reservoir: Rebuild Transmission Line CrossingsDESC:06810 Gno overlap
    • Estimated cost
      $9,655,669changed to$9,678,370+0.2% as filed
      DESC filing 2024-2028, p. 27 → DESC filing 2025-2029, p. 22
    • In-service date
      2024-12-31changed to2025-10-31filed date moved 304 days later between filingshistorical
      DESC filing 2024-2028, p. 27 → DESC filing 2025-2029, p. 22
  11. Dominion Energy SCSummerville 115kV Loop: RebuildDESC:06810 Hno overlap
    • In-service date
      2024-12-31changed to2025-12-31filed date moved 365 days later between filingshistorical
      DESC filing 2024-2028, p. 28 → DESC filing 2025-2029, p. 23
  12. Dominion Energy SCWilliams St Sub: Replace Sw House & Relays, AM Williams Sub: Replace Sw House, and McMeekin Sub: Add Sw HouseDESC:1060A, I, Lno overlap
    • Estimated cost
      $9,898,924changed to$11,182,924+13.0% as filed
      DESC filing 2024-2028, p. 17 → DESC filing 2025-2029, p. 13
  13. Dominion Energy SCCoit – Gills Creek 115kV: ConstructDESC:5392 A-Cno overlap
    • Estimated cost
      $2,509,602changed to$5,773,202+130.0% as filed
      DESC filing 2024-2028, p. 30 → DESC filing 2025-2029, p. 25
    • In-service date
      2024-12-31changed to2025-12-31filed date moved 365 days later between filingshistorical
      DESC filing 2024-2028, p. 30 → DESC filing 2025-2029, p. 25
  14. Dominion Energy SCCainhoy - Hamlin 115kV: Rebuild Line and Cainhoy – Hamlin 115 kV #2: Construct New 115 kV LineDESC:6341 A-Fno overlap
    • Estimated cost
      $19,890,850changed to$31,362,092+57.7% as filed
      DESC filing 2024-2028, p. 4 → DESC filing 2025-2029, p. 3
    • In-service date
      2025-12-01changed to2026-12-02filed date moved 366 days later between filings
      DESC filing 2024-2028, p. 4 → DESC filing 2025-2029, p. 3
  15. Dominion Energy SCYemassee– Ritter 230kV #1 & #2: Construct SPDC with B-1272DESC:6359no overlap
    • Estimated cost
      $40,611,419changed to$45,032,777+10.9% as filed
      DESC filing 2024-2028, p. 21 → DESC filing 2025-2029, p. 16
    • In-service date
      2026-06-01changed to2027-06-01filed date moved 365 days later between filings
      DESC filing 2024-2028, p. 21 → DESC filing 2025-2029, p. 16
    • Status
      Plannedchanged toIn Progress
      DESC filing 2024-2028, p. 21 → DESC filing 2025-2029, p. 16
  16. Dominion Energy SCWilliams-Summerville 230kV: Upgrade to SPDC B1272 ACSRDESC:6388 Ano overlap
    • Estimated cost
      $19,300,000changed to$25,500,000+32.1% as filed
      DESC filing 2024-2028, p. 36 → DESC filing 2025-2029, p. 30
    • In-service date
      2027-05-01changed to2028-12-31filed date moved 610 days later between filings
      DESC filing 2024-2028, p. 36 → DESC filing 2025-2029, p. 30
    • Status
      Plannedchanged toIn Progress
      DESC filing 2024-2028, p. 36 → DESC filing 2025-2029, p. 30
  17. Dominion Energy SCEdenwood Sub: #1 & #2 230-115kV Autobanks, Replace with 336MVADESC:6805 Gno overlap
    • Estimated cost
      $10,833,462changed to$9,821,256-9.3% as filed
      DESC filing 2024-2028, p. 16 → DESC filing 2025-2029, p. 12
    • In-service date
      2024-12-25changed to2025-06-30filed date moved 187 days later between filingshistorical
      DESC filing 2024-2028, p. 16 → DESC filing 2025-2029, p. 12
  18. Dominion Energy SCBurton-St Helena 115kV: Rebuild Burton-Frogmore Transmission SectionDESC:6808 Kno overlap
    • Estimated cost
      $8,580,000changed to$12,000,000+39.9% as filed
      DESC filing 2024-2028, p. 6 → DESC filing 2025-2029, p. 4
    • In-service date
      2024-12-31changed to2025-04-30filed date moved 120 days later between filingshistorical
      DESC filing 2024-2028, p. 6 → DESC filing 2025-2029, p. 4
  19. Dominion Energy SCBurton-St Helena 115kV: Frogmore Distribution - St HelenaDESC:6808 Lno overlap
    • Estimated cost
      $6,925,000changed to$18,825,000+171.8% as filed
      DESC filing 2024-2028, p. 7 → DESC filing 2025-2029, p. 5
    • In-service date
      2025-12-31changed to2027-12-31filed date moved 730 days later between filings
      DESC filing 2024-2028, p. 7 → DESC filing 2025-2029, p. 5
  20. Dominion Energy SCVCS1-Denny Terrace 230kV & VCS1-Pineland 230kV: Rebuild Single Circuit SectionsDESC:6808 N,Ono overlap
    • Estimated cost
      $4,912,096changed to$8,667,157+76.4% as filed
      DESC filing 2024-2028, p. 8 → DESC filing 2025-2029, p. 6
    • In-service date
      2026-12-31changed to2027-12-31filed date moved 365 days later between filings
      DESC filing 2024-2028, p. 8 → DESC filing 2025-2029, p. 6
  21. Dominion Energy SCOkatie-Bluffton 115kV: RebuildDESC:6808 Sin 1 overlap →
    • Estimated cost
      $40,660,000changed to$40,674,739+0.0% as filed
      DESC filing 2024-2028, p. 10 → DESC filing 2025-2029, p. 8
  22. Dominion Energy SCHopkins-CIP 230kV: RebuildDESC:6808 Uno overlap
  23. Dominion Energy SCFaber Place-Bayfront 115kV: Rebuild North Bridge Terrace to Bayfront SectionDESC:6808 Vno overlap
  24. Dominion Energy SCHooks - Modoc 115/46 kV RebuildDESC:6809 Gin 3 overlaps →
    • In-service date
      2025-12-31changed to2027-12-31filed date moved 730 days later between filings
      DESC filing 2024-2028, p. 15 → DESC filing 2025-2029, p. 11
    • Project name
      Stevens Creek - Hooks 115kV/LR Plumb Branch 46kVchanged toHooks - Modoc 115/46 kV Rebuild
      DESC filing 2024-2028, p. 15 → DESC filing 2025-2029, p. 11
    • Status
      Plannedchanged toIn Progress
      DESC filing 2024-2028, p. 15 → DESC filing 2025-2029, p. 11
  25. Dominion Energy SCSt George - Sumter 230kV Tie: Rebuild Line from Santee Substation - Duke/Progress Energy TieDESC:6809 Mno overlap
    • Estimated cost
      $4,000,000changed to$5,000,000+25.0% as filed
      DESC filing 2024-2028, p. 29 → DESC filing 2025-2029, p. 24
    • In-service date
      2025-12-31changed to2027-12-31filed date moved 730 days later between filings
      DESC filing 2024-2028, p. 29 → DESC filing 2025-2029, p. 24
    • Status
      Plannedchanged toIn Progress
      DESC filing 2024-2028, p. 29 → DESC filing 2025-2029, p. 24
  26. Dominion Energy SCElloree – Santee City 46 kV: RebuildDESC:6810 Jno overlap
  27. Dominion Energy SCCameron Jct – Cameron – St Matthews 46 kV RebuildDESC:6810 Tno overlap
    • Estimated cost
      $5,900,000changed to$8,550,000+44.9% as filed
      DESC filing 2024-2028, p. 44 → DESC filing 2025-2029, p. 38
  28. Dominion Energy SCCameron Jct – Elloree 46 kV RebuildDESC:6810 Uno overlap
    • Estimated cost
      $4,500,000changed to$6,615,000+47.0% as filed
      DESC filing 2024-2028, p. 41 → DESC filing 2025-2029, p. 35
    • In-service date
      2026-12-31changed to2027-12-31filed date moved 365 days later between filings
      DESC filing 2024-2028, p. 41 → DESC filing 2025-2029, p. 35
  29. Dominion Energy SCEastover – Sumter 115kV DEP Tie: Rebuild with 1272 ACSRDESC:6846 Ano overlap
  30. Dominion Energy SCScout 230 kV Sub and Fold-in: ConstructDESC:6853 B-Fno overlap
    • Estimated cost
      $23,685,000changed to$28,579,145+20.7% as filed
      DESC filing 2024-2028, p. 33 → DESC filing 2025-2029, p. 27
  31. Dominion Energy SCDawson 230kV Sub and Fold-in: Construct and RebuildDESC:6859no overlap
    • Estimated cost
      $93,538,207changed to$93,603,207+0.1% as filed
      DESC filing 2024-2028, p. 34 → DESC filing 2025-2029, p. 28