Filing changes
The same project compared across two filings: 58 changed fields on 31 projects. A changed in-service date is a change in the filing, not evidence of a current delay.
- Dominion Energy SCOkatie 230-115kV Substation, Jasper – Yemassee 230kV #1 Fold-in
DESC:0139 M,Nverified exampleno overlap- Estimated cost$11,116,933changed to$11,630,257+4.6% as filed
- In-service date2024-12-31changed to2026-05-31filed date moved 516 days later between filingshistorical
- Dominion Energy SCJack Primus 115 kV Tap: Construct
DESC:0147 B, Jno overlap- Estimated cost$18,000,000changed to$17,955,000-0.3% as filed
- In-service date2027-12-31changed to2028-12-31filed date moved 366 days later between filings
- Dominion Energy SCCainhoy 115 kV Tap: Construct
DESC:0147 C, Kno overlap- Estimated cost$21,850,000changed to$21,800,000-0.2% as filed
- In-service date2027-12-31changed to2028-12-31filed date moved 366 days later between filings
- Dominion Energy SCCanadys-Ritter 115KV-Rebld SPDC 230/115KV 1272 (Approx 18 Miles)
DESC:06076Ano overlap- Estimated cost$40,000,000changed to$38,041,268-4.9% as filed
- In-service date2026-06-01changed to2028-06-01filed date moved 731 days later between filings
- Dominion Energy SCSherwood Tap: Construct Tap
DESC:06367 A - C, Hno overlap- Estimated cost$34,877,427changed to$54,446,256+56.1% as filed
- In-service date2025-12-31changed to2026-05-31filed date moved 151 days later between filingshistorical
- Project nameRiverport Tap: Construct Tapchanged toSherwood Tap: Construct Tap
- Estimated cost$23,787,423changed to$28,578,734+20.1% as filed
- In-service date2025-12-31changed to2026-05-31filed date moved 151 days later between filingshistorical
- Dominion Energy SCWagener 115kV Tap: Construct Tap
DESC:06371 Dno overlap- In-service date2025-12-31changed to2027-12-31filed date moved 730 days later between filings
- Dominion Energy SCChurch Creek - Ritter 230kV - Replace 38 Large Angles and Dead Ends
DESC:06372 Ano overlap- Estimated cost$10,850,000changed to$11,401,163+5.1% as filed
- In-service date2024-06-01changed to2025-12-31filed date moved 578 days later between filingshistorical
- Dominion Energy SCVCS2-Ward 230kV: Rebuild Line
DESC:06810 Fno overlap- Estimated cost$30,000,000changed to$38,275,000+27.6% as filed
- Dominion Energy SCGoose Creek Reservoir: Rebuild Transmission Line Crossings
DESC:06810 Gno overlap- Estimated cost$9,655,669changed to$9,678,370+0.2% as filed
- In-service date2024-12-31changed to2025-10-31filed date moved 304 days later between filingshistorical
- Dominion Energy SCSummerville 115kV Loop: Rebuild
DESC:06810 Hno overlap- In-service date2024-12-31changed to2025-12-31filed date moved 365 days later between filingshistorical
- Dominion Energy SCWilliams St Sub: Replace Sw House & Relays, AM Williams Sub: Replace Sw House, and McMeekin Sub: Add Sw House
DESC:1060A, I, Lno overlap- Estimated cost$9,898,924changed to$11,182,924+13.0% as filed
- Dominion Energy SCCoit – Gills Creek 115kV: Construct
DESC:5392 A-Cno overlap- Estimated cost$2,509,602changed to$5,773,202+130.0% as filed
- In-service date2024-12-31changed to2025-12-31filed date moved 365 days later between filingshistorical
- Dominion Energy SCCainhoy - Hamlin 115kV: Rebuild Line and Cainhoy – Hamlin 115 kV #2: Construct New 115 kV Line
DESC:6341 A-Fno overlap- Estimated cost$19,890,850changed to$31,362,092+57.7% as filed
- In-service date2025-12-01changed to2026-12-02filed date moved 366 days later between filings
- Dominion Energy SCYemassee– Ritter 230kV #1 & #2: Construct SPDC with B-1272
DESC:6359no overlap- Estimated cost$40,611,419changed to$45,032,777+10.9% as filed
- In-service date2026-06-01changed to2027-06-01filed date moved 365 days later between filings
- StatusPlannedchanged toIn Progress
- Dominion Energy SCWilliams-Summerville 230kV: Upgrade to SPDC B1272 ACSR
DESC:6388 Ano overlap- Estimated cost$19,300,000changed to$25,500,000+32.1% as filed
- In-service date2027-05-01changed to2028-12-31filed date moved 610 days later between filings
- StatusPlannedchanged toIn Progress
- Dominion Energy SCEdenwood Sub: #1 & #2 230-115kV Autobanks, Replace with 336MVA
DESC:6805 Gno overlap- Estimated cost$10,833,462changed to$9,821,256-9.3% as filed
- In-service date2024-12-25changed to2025-06-30filed date moved 187 days later between filingshistorical
- Dominion Energy SCBurton-St Helena 115kV: Rebuild Burton-Frogmore Transmission Section
DESC:6808 Kno overlap- Estimated cost$8,580,000changed to$12,000,000+39.9% as filed
- In-service date2024-12-31changed to2025-04-30filed date moved 120 days later between filingshistorical
- Dominion Energy SCBurton-St Helena 115kV: Frogmore Distribution - St Helena
DESC:6808 Lno overlap- Estimated cost$6,925,000changed to$18,825,000+171.8% as filed
- In-service date2025-12-31changed to2027-12-31filed date moved 730 days later between filings
- Dominion Energy SCVCS1-Denny Terrace 230kV & VCS1-Pineland 230kV: Rebuild Single Circuit Sections
DESC:6808 N,Ono overlap- Estimated cost$4,912,096changed to$8,667,157+76.4% as filed
- In-service date2026-12-31changed to2027-12-31filed date moved 365 days later between filings
- Estimated cost$40,660,000changed to$40,674,739+0.0% as filed
- Dominion Energy SCHopkins-CIP 230kV: Rebuild
DESC:6808 Uno overlap- Estimated cost$2,600,000changed to$3,500,000+34.6% as filed
- StatusPlannedchanged toIn Progress
- Dominion Energy SCFaber Place-Bayfront 115kV: Rebuild North Bridge Terrace to Bayfront Section
DESC:6808 Vno overlap- Estimated cost$10,200,000changed to$13,218,768+29.6% as filed
- StatusPlannedchanged toIn Progress
- In-service date2025-12-31changed to2027-12-31filed date moved 730 days later between filings
- Project nameStevens Creek - Hooks 115kV/LR Plumb Branch 46kVchanged toHooks - Modoc 115/46 kV Rebuild
- StatusPlannedchanged toIn Progress
- Dominion Energy SCSt George - Sumter 230kV Tie: Rebuild Line from Santee Substation - Duke/Progress Energy Tie
DESC:6809 Mno overlap- Estimated cost$4,000,000changed to$5,000,000+25.0% as filed
- In-service date2025-12-31changed to2027-12-31filed date moved 730 days later between filings
- StatusPlannedchanged toIn Progress
- Dominion Energy SCElloree – Santee City 46 kV: Rebuild
DESC:6810 Jno overlap- Estimated cost$4,500,000changed to$8,200,000+82.2% as filed
- StatusPlannedchanged toIn Progress
- Dominion Energy SCCameron Jct – Cameron – St Matthews 46 kV Rebuild
DESC:6810 Tno overlap- Estimated cost$5,900,000changed to$8,550,000+44.9% as filed
- Dominion Energy SCCameron Jct – Elloree 46 kV Rebuild
DESC:6810 Uno overlap- Estimated cost$4,500,000changed to$6,615,000+47.0% as filed
- In-service date2026-12-31changed to2027-12-31filed date moved 365 days later between filings
- Dominion Energy SCEastover – Sumter 115kV DEP Tie: Rebuild with 1272 ACSR
DESC:6846 Ano overlap- StatusPlannedchanged toIn Progress
- Dominion Energy SCScout 230 kV Sub and Fold-in: Construct
DESC:6853 B-Fno overlap- Estimated cost$23,685,000changed to$28,579,145+20.7% as filed
- Dominion Energy SCDawson 230kV Sub and Fold-in: Construct and Rebuild
DESC:6859no overlap- Estimated cost$93,538,207changed to$93,603,207+0.1% as filed